Provision of Engineering for Pipeline River Crossing on Single Span Bridge Design

CLIENT DNO Iraq AS
SCOPE OF WORK Engineering
PROJECT LOCATION Kurdistan, Iraq
DURATION 90 Days
START DATE Oct-22
COMPLETION DATE Jan-23 (Extension)
PROJECT DESCRIPTION

This pipeline traverses over the Khabour River via an underwater crossing, at which the original design was to bury the pipeline below the riverbed. During recent inspections, it was found that the pipeline was exposed at the Tawke side of the river crossing, and approximately 15 to 20mlengthofthepipelinewas found to be unsupported.