Detailed Design for Business Continuity – Gas In, Gas Out
SCOPE OF WORK :
LOCATION : Kurdistan Region of Iraq
DURATION : 18 Weeks
START DATE : May-25
COMPLETION DATE : Nov-25
DESCRIPTION
Detailed design for emergency bypass routes at Khor Mor LPG Plant to ensure continued export of Natural Gas and NGL during security-related disruptions, enabling direct flow from inlet separators to export lines.

Technical Service for WQ2 Yamama Re-Feed Project Gathering System (Package B1 and B2)
CLIENT :
SCOPE OF WORK :
LOCATION : Iraq
DURATION : 3 months
START DATE : Feb-25
COMPLETION DATE : Apr-26
DESCRIPTION
Re-FEED for the Yamama Field since the plateau was changed from 650 MBOPD to 350 MBOPD. The scope is limited to B1/B2 package with new well pads and wells along with the tie-in to the pilot wells. This scope include the treatment of oil production, gas processing plant and produced water treatment.

Pre-Bid Engineering Support for EPC of Mishrif Wellpad & Dammam Well Upgrades for West Qurna 2
CLIENT :
SCOPE OF WORK :
LOCATION : Iraq
DURATION : 6 months
START DATE : Jan-25
COMPLETION DATE : Jul-25
DESCRIPTION
Pre-bid engineering support for Mishrif Wellpads & associated Gathering Systems and Dammam Well upgrades. Provide support in preparation of material requisitions (MR), material take-offs (MTO), bill of quantity (BOQ), data sheets (DS), Vendor Data Requisition (VDR), pre-bid engineering, and FEED endorsement.

Engineering Services for Well ST-B2 to Choke Skid Slot 7
CLIENT :
SCOPE OF WORK :
LOCATION : Kurdistan Region of Iraq
DURATION : 6 months
START DATE : Dec-24
COMPLETION DATE : TBA
DESCRIPTION
Detailed Engineering (Multidiscipline) for Well ST-B2 to Choke Skid Slot B7.

Tanker Loading Engineering Detailed Design
CLIENT :
SCOPE OF WORK :
LOCATION : Kurdistan Region of Iraq
DURATION : 2 Months
START DATE : Oct-24
COMPLETION DATE : Dec-24
DESCRIPTION
A Tanker Loading Station (TLS) is proposed as a fast-track project to enhance export flexibility in the Atrush field, addressing the current limitation of pipeline-only exports. The TLS will facilitate crude oil loadout for transportation to regional refineries via road. The project involves relocating an existing two-bay loading station to Terrace 4 within the Atrush CPF facility, aiming for completion within 60 days of award. Construction will occur in two phases: Phase One will provide approximately 15,000 barrels of oil per day (bopd) using existing equipment, while Phase Two will expand capacity to approximately 45,000 bopd by adding three additional twin-arm loading stations. The scope includes validating the Phase 1 engineering proposal and managing associated risks.
Conducted Flow Assurance Study for the Soluforce Crude Oil Loading System.

Tanker Loading Engineering Detailed Design
CLIENT :
SCOPE OF WORK :
LOCATION : Kurdistan Region of Iraq
DURATION : 8 months
START DATE : Oct-24
COMPLETION DATE : Completed
DESCRIPTION
Detail engineering design support for tanker loading expansion to 15,000 BPD, which includes the provision of two (2) loading bays.

Secondment Agreement – Process Engineer
CLIENT :
SCOPE OF WORK :
LOCATION : UK/Gabon
DURATION : 3 Months (Extendable)
START DATE : Jun-24
COMPLETION DATE : Sep-24
DESCRIPTION
Provide facilities conceptual engineering, cost estimating, and business case development support for early-stage brownfield projects, including GHG emissions reduction opportunities and stewardship. Offer overall project management support, coordinating multi-discipline activities and external contractors to develop innovative and feasible project solutions.

Engineering Services for Site Survey
CLIENT :
SCOPE OF WORK :
LOCATION : Iraq
DURATION : 1 Month
START DATE : Mar-24
COMPLETION DATE : Apr-24
DESCRIPTION
Site and Facilities Verification for EPC for Gas Sweetening Unit Modification, Nitrogen Package and Raw Gas Compression & Dehydration Facilities at the West Qurna (Phase 2) Contract Area.

Water Flood Injection Pump Replacement Concept Design
CLIENT :
SCOPE OF WORK :
LOCATION : Libya
DURATION : 4 Months
START DATE : Feb-24
COMPLETION DATE : Jun-24
DESCRIPTION
Conduct basic engineering, evaluate layout options, develop a concept-level E&I integration scheme, estimate costs for high-value and Long Lead Items, contact vendors for three options, and provide a Level 4 cost estimate and Level 2 management summary schedule.

Detail Design of Permanent Power Supply through Overhead Line (KPS2 to RETM) and Establishment of New Substation in RETM
CLIENT :
SCOPE OF WORK :
LOCATION : Kurdistan Region of Iraq
DURATION : 5 Months
START DATE : Nov-23
COMPLETION DATE : Jun-24
DESCRIPTION
Conduct OHTL engineering, covering but not limited to:
11kV OHL Design, 16 km, between KPS2 and RETM;
11 kV Integrated Substation at RETM ;
Electrical Cabling between the OHL and the Integrated New Substation.

Human Factors Engineering Study
CLIENT :
SCOPE OF WORK :
LOCATION : UAE
DURATION : 4 Months
START DATE : Sep-23
COMPLETION DATE : Dec-23
DESCRIPTION
The Scope of Work includes, but not limited to:
Human Factor for FEED phase of the Facilities described above, including non-licenced and licenced systems.
Analysis, review, desktop activities, workshops and production of the corresponding studies and applicable reports.
Execute this study in compliance with the relevant Client CoPs & Specification, HSE Guidelines and International Standards.

Nasiriyah & Gharaff Flare Gas Treatment Project – Iraq
CLIENT :
SCOPE OF WORK :
LOCATION : Iraq
DURATION : 24 Months
START DATE : Sep-23
COMPLETION DATE : Sep-25
DESCRIPTION
Engineering Review & Audit Services for Nasiriyah & Gharaff Flare Gas Treatment Project – Iraq

Provision of Third Party Technical Review for Paloch De-Bottlenecking (DBN) Facilities
CLIENT :
SCOPE OF WORK :
LOCATION : South Sudan
DURATION : 11 Months
START DATE : Jul-23
COMPLETION DATE : Jun-24
DESCRIPTION
Evaluate the Process Issues with the aim of de-bottlenecking the facility to achieve the original design intent. Conduct Site Visit and Sampling to inform de-bottlenecking recommendations. Adhere to DPOC Standards & Codes, South Sudan’s Rules, Regulations, and Laws, and International Standards and Best Practice

Flare and Relief Sizing Verification Services
CLIENT :
SCOPE OF WORK :
LOCATION : Iraq
DURATION : 2 Months
START DATE : Jun-23
COMPLETION DATE : Jul-23
DESCRIPTION
Work to be provided comprise the following:
Perform a detailed design verification of the Flare and Relief Systems for the West Qurna I (WQI) Oil Trains 2 and 3 located at Degassing Station 7 (DS7) and Degassing Station 6 (DS6);
Lead the flare and relief sizing verification works;
Integrated Engineering Management Team;
Performing Sizing Calculations
Review of Flare Net Model Network;
Study for Acoustically Induced Vibration (AIV) for PSVs
Flare radiation / dispersion Calculations Excluded for 3rd Party Scope

Engineering Services for Site Survey
CLIENT :
SCOPE OF WORK :
LOCATION : Kurdistan Region of Iraq
DURATION : 9 Months
START DATE : Jul-23
COMPLETION DATE : Apr-24
DESCRIPTION
The Services to be provided under the Contract may include, but not be limited to:
Project management;
Detailed Engineering for the 24 inch, 16 Km Pipeline between RETM & KRS2;
Conduct Geo and Topo Survey;
Upgrade the RTU/SCADA Systems;
Carried out Flow Assurance Study to ensure stable oil transport between RETM & KRS2;
Preparation of the PC Scope of Work;
Preparation of the PC Cost Estimate;
Preparation of the PC Schedule;
Preparation of the Project Dossier.

Call-Off Contract for the Provision of Engineering Consultancy Services
CLIENT :
SCOPE OF WORK :
LOCATION : Kurdistan Region of Iraq
DURATION : 24 months (Extended)
START DATE : May-23
COMPLETION DATE : Apr-25
DESCRIPTION
The Services to be provided under the Contract may include, but not be limited to:
- Feasibility studies and frontend engineering studies;
- Detailed design activities, including preparation of procurement documentation (invitation to tender packages) and technical bid evaluations;
- Provision of personnel to work within TAQA’s organization;
- Upgrade the DCS/ESD/FGS Systems;
- Preparation of the EPC Scope of Work;
- Preparation of the EPC Cost Estimate;
- Preparation of the EPC Schedule;
- Preparation of the Project Dossier.

Project Management Site Services
CLIENT :
SCOPE OF WORK :
LOCATION : Kurdistan Region of Iraq
DURATION : 18 Months
START DATE : Mar-23
COMPLETION DATE : Aug-25
DESCRIPTION
Contractor shall provide the required personnel, and personnel management to support TAQA’s project activities as required.

Detailed Design Study for Sour Gas Incinerator with WHRU
CLIENT :
SCOPE OF WORK :
LOCATION : Kurdistan Region of Iraq
DURATION : 5 months
START DATE : Feb-23
COMPLETION DATE : Jun-23
DESCRIPTION
Install a MODIFICATION that includes a Sour Gas Incinerator with associated Waste Heat Recovery Unit (WHRU). This will reduce the visible flare by burning the Gas in the Incinerator. The high temperature exhaust gas from the Incinerator will pass through a WHRU, which shall be integrated into a New Hot Oil System, which is used for on-site process heating requirements.

Technical Service for Engineering Projects in MEDC for Year 2023 & 2024
CLIENT :
SCOPE OF WORK :
LOCATION : UAE
DURATION : 24 Months
START DATE : Dec-22
COMPLETION DATE : Dec-24 Cancelled. A new contract has been established
DESCRIPTION
Provide required Technical Service to support COMPANY for carrying out design engineering, detailed engineering, technical support for procurement activities such as; Material Requisitions (MRs), Technical Bids Evaluations (TBEs) & Vendor Data Requirements (VDRs), as well as support for the project management, planning, control, cost control, document control, construction, and commissioning Work, as required.

Provision of Engineering for Pipeline River Crossing on Single Span Bridge Design
CLIENT :
SCOPE OF WORK :
LOCATION : Kurdistan Region of Iraq
DURATION : 90 Days
START DATE : Oct-22
COMPLETION DATE : Jan-23
DESCRIPTION
This pipeline traverses over the Khabour River via an underwater crossing, at which the original design was to bury the pipeline below the riverbed. During recent inspections, it was found that the pipeline was exposed at the Tawke side of the river crossing, and approximately 15 to 20m length of the pipeline was found to be unsupported.

Fire Gas Detection – Layout Assessment
CLIENT :
SCOPE OF WORK :
LOCATION : Kurdistan Region of Iraq
DURATION : 5 Weeks
START DATE : Sept-22
COMPLETION DATE : OCT-22
DESCRIPTION
The scope of work for this project is limited to:
Assess the robustness and reliability of the mitigation barrier associated with the existing point detector network for the detection/confirmation of a flammable and/or toxic gas release with the existing LOS detection system removed from the Safety Instrumented System (SIS);
Study to evaluate whether the point detected currently provided is adequate. If inadequate, include a pragmatic recommendation to achieve the required barrier robustness;
The study shall be limited to FZ-4 & FZ-9;
The coverage of the detectors considered in the study is manufactured by M/S DECTON.

Provision of Engineering Consultancy Services
CLIENT :
SCOPE OF WORK :
LOCATION : Kurdistan Region of Iraq
DURATION : 33 Months
START DATE : Jul-22
COMPLETION DATE : Dec-25
DESCRIPTION
Call-Out Contract for the provision of engineering consultancy services for the Garmian block, located in the Kurdistan Autonomous Region, Republic of Iraq. This includes: ETAP power system study for the 11kV network at Sarqala 3 and 4; Detailed design for a 5km, 11kV overhead line (OHL). This scope include the treatment of oil production, gas processing plant and produced water treatment.

Pre-FEED, FEED, Detailed Design, Engineering and Support Services
CLIENT :
SCOPE OF WORK :
LOCATION : UAE
DURATION : 24 Months
START DATE : Jun-22
COMPLETION DATE : Jun-24
DESCRIPTION
The Services to be provided cover, but are not limited to, the following core activities:
Project Management
Documentation Management
Engineering Management
Engineering Calculations and Simulations
Equipment Design and Material Requisitions
Preparation of Fabrication, Construction, Installation, and/or Commissioning Drawings
Preparation of Specifications, Procedures and/or Philosophies
Preparation of an integrated 2D and 3D models
Preparation of As-Builts

Peshkabir 2nd Stage Gas Capture / Tawke AGI Optimization Concept Techno-Economic Screening Study Proposal
CLIENT :
SCOPE OF WORK :
LOCATION : Kurdistan Region of Iraq
DURATION : 7 Weeks
START DATE : Feb-22
COMPLETION DATE : Dec-22
DESCRIPTION
To explore possible options and provide recommendation for the Peshkabir 2nd stage separator associated gas capture and enhance the gas handling compression and injection.

FEED Design of Fire Suppression System
CLIENT :
SCOPE OF WORK :
LOCATION : Kurdistan Region of Iraq
DURATION : 32 Weeks
START DATE : Feb-22
COMPLETION DATE : Sep-22
DESCRIPTION
FEED for Fire Suppression System at three main stations of KPS1, KPS2 and RETM.

Provision Of Engineering Call-Off Services for Phases 1B, 1C and 1D
SCOPE OF WORK :
LOCATION : Kurdistan Region of Iraq
DURATION : 24 Months + 12 Months Extension (Optional)
START DATE : Jan-22
COMPLETION DATE : Feb-25
DESCRIPTION
Provision of Engineering support on an ad-hoc Call Off basis in developing the Shaikan Field in Northern Kurdistan. This scope include the treatment of oil production, gas processing plant and produced water treatment. Concept of 5,000 BBL per day capacity of EPF was executed as a part of this GSA.

Engineering Study for Rectification of Electrical Defects at KPS0 Station
SCOPE OF WORK :
LOCATION : Kurdistan Region of Iraq
DURATION : 16 Weeks
START DATE : Jan-22
COMPLETION DATE : May-22
DESCRIPTION
Engineering study for rectifications works on defective electrical equipment, material, components, and instruments. The works include investigation, engineering study, design and engineering documentation and drawings for the systems.

Consultancy Services for Sarsang and Atrush Field Gas Processing Facility Study
CLIENT :
SCOPE OF WORK :
LOCATION : Kurdistan Region of Iraq
DURATION : 6 Weeks
START DATE : Nov-21
COMPLETION DATE : Jan-23
DESCRIPTION
Provision of Consultancy Services for Sarsang and Atrush Field Gas Processing Facility Study. This scope include the treatment of oil production, gas processing plant and produced water treatment.

Provision of Electrical, Instrument & Mechanical Manpower Service
CLIENT :
SCOPE OF WORK :
LOCATION : Kurdistan Region of Iraq
DURATION : 12 Months
START DATE : Aug-21
COMPLETION DATE : Aug-22
DESCRIPTION
Contractor shall provide the required personnel, and personnel management to support TAQA’s
project activities as required.

Safety Study of Anokyi Mainline Compressor Station (AMCS) Phase II EPCC Project
SCOPE OF WORK :
LOCATION : Ghana
DURATION : 6 Months
START DATE : May-21
COMPLETION DATE : Oct-21
DESCRIPTION
To conduct the following study for the Anokyi Mainline Compressor Station (AMCS) Phase II EPCC Project of Meridian Logistic and Engineering (MLE) on behalf of Ghana National Gas Company:
SIMOPS study;
HAZOP study;
SIL (LOPA) study;
FERA; and
QRA study.

Provision of Engineering and Design Services for the Block 11 Field Development Projects
CLIENT :
SCOPE OF WORK :
LOCATION : Kurdistan Region of Iraq
DURATION : 36 Months
START DATE : Feb-21
COMPLETION DATE : Feb-24
DESCRIPTION
Concept, FEED and Detailed Engineering for Block 11 Field.
The Services to be provided under the Contract may include, but not be limited to:
Feasibility studies and frontend engineering studies for the process facility;
Detailed design activities for the process facility, offsite, pipeline, and OHL, and that includes preparation of procurement documentation (invitation to tender packages) and technical bid evaluations;
Conducted Flow Assurance Study for Bejil Field Soluforce Production Trunkline;
Conducted Flow Assurance Study for Soluforce Water Disposal System.
This scope includes the leased EPF early production facility of 10,000 BBL per day and the upgrade of existing treatment of oil production, gas processing plant and produced water treatment.

Engineering for Rectification of 36 Electrical Category 1 Defects
SCOPE OF WORK :
LOCATION : Kurdistan Region of Iraq
DURATION : 4 Months
START DATE : Dec-20
COMPLETION DATE : Mar-21
DESCRIPTION
To perform Engineering Design calculations for the repairs and rectification of 36 Electrical Category 1 Defects.
To produce Engineering Design calculations, Bill of Quantities, Specifications, Detailed Engineering Drawings for Defects located within Battery Limit of Stations and identify the gap between the design parameters against the operating requirements of the equipment / item / system.
The scope also includes conducting site survey, investigation and obtaining all historical as well as present operations data of the equipment / item / system.

Provision of Design and Engineering Services for Firefighting System at CPF Sarqala-1 Wellsite, Garmian Block, Kurdistan
CLIENT :
SCOPE OF WORK :
LOCATION : Kurdistan Region of Iraq
DURATION : Approx. 18 Months
START DATE : Oct-20
COMPLETION DATE : Nov-21
DESCRIPTION
Carry out all necessary Engineering works related to Fire-fighting system for CPF S-1 Facilities in accordance with NPFA standard.
The firefighting equipment consist of Water Supply, Fire Water Tanks feeding the Fire Ring; Fire Pumps; Hydrants, Hydro-Foam Monitors, Post Indicator Valves; Deluge system at the new tanks; Sprinklers under the roof over loading bay and portable and wheeled fire extinguishers.

Provision of Leased Oil Train (LOT), Garraf, Iraq Provision of O&M Services (Garraf Project)
CLIENT :
SCOPE OF WORK :
LOCATION : Iraq
DURATION : 12 Months
START DATE : Feb-20
COMPLETION DATE : Jan-22
DESCRIPTION
To provide Operation & Maintenance (O&M) Services for Petronas Carigali Iraq Holding B.V. on behalf of Italfluid.

Provision of Engineering Services
CLIENT :
SCOPE OF WORK :
LOCATION : Kurdistan Region of Iraq
DURATION : 30 Months
START DATE : Nov-19
COMPLETION DATE : May-22
DESCRIPTION
To perform Feasibility studies and front-end engineering studies, Detailed design activities including preparation of procurement documentation (invitation to tender packages) and technical bid evaluations, provision of personnel to work within TAQA’s organization, and provision of any other work and Services incidental to the foregoing including ‘as building’ documentation, survey works, minor plant changes, etc.

Provision of Engineering Services
CLIENT :
SCOPE OF WORK :
LOCATION : UAE/Iraq
DURATION : -
START DATE : Oct-19
COMPLETION DATE : Apr-22
DESCRIPTION
To provide Engineering Support for different ongoing Projects.

Provision of Leased Oil Train (LOT), Garraf, Iraq Consultancy Agreement for Site Works
CLIENT :
SCOPE OF WORK :
LOCATION : Iraq
DURATION : 18 Months
START DATE : Aug-19
COMPLETION DATE : Feb-21
DESCRIPTION
Provision of Site/Construction Supervision for Petronas Carigali Iraq Holding B.V. on behalf of Italfluid.

Provision of Leased Oil Train (LOT), Garraf, Iraq Design, Supply and Configuration of DCS & Integrated Safety System
CLIENT :
SCOPE OF WORK :
LOCATION : Iraq
DURATION : 8 Months
START DATE : May-19
COMPLETION DATE : Jan-20
DESCRIPTION
Provision of Design, Supply and Configuration of DCS & Integrated Safety System for Leased Oil Train, Petronas, Iraq.

HAZOP, IPF & HAZID Studies
CLIENT :
SCOPE OF WORK :
LOCATION : Iraq
DURATION : 2-4 weeks
START DATE : May-19
COMPLETION DATE : Jun-19
DESCRIPTION
Provision of HAZOP, IPF & HAZID Studies for the Provision of Leased Oil Train Including Operations and Maintenance for Petronas Carigali Iraq Holding B.V (PCIHBV).

Provision of Leased Oil Train (LOT), Garraf, Iraq
CLIENT :
SCOPE OF WORK :
LOCATION : Iraq
DURATION : 20 Months
START DATE : Feb-19
COMPLETION DATE : Oct-20
DESCRIPTION
Engineering design works for 30,000 BBL per day including but not limited to the detailed Engineering design, record drawings and documentation.

Provision of Engineering Services
CLIENT :
SCOPE OF WORK :
LOCATION : Kurdistan Region of Iraq
DURATION : 24 Months
START DATE : Feb-19
COMPLETION DATE : Feb-21
DESCRIPTION
To perform engineering, detailed design including all analyses, procurement personnel support, preparation of operation and maintenance manuals, Commissioning and Start–up assistance to Company’s Operations Group as required and for the provision of all records / documentation necessary for the complete performance of the Work.
Also responsible for all aspects of the Services, with regard to Health, Safety, Security and Environmental (HSSE) performance, quality management, schedule, cost, and functionality.

Provision of Engineering Services
CLIENT :
SCOPE OF WORK :
LOCATION : Iraq
DURATION : 24 months
START DATE : Jan-19
COMPLETION DATE : Cancelled
DESCRIPTION
To provide engineering studies, cost estimation and engineering interpretation primarily but not solely aimed at identifying, evaluating, and designing oil and gas surface facilities in Northern Iraq.

Framework Agreement for a Project Management Contract
CLIENT :
SCOPE OF WORK :
LOCATION : Algeria
DURATION : 60 months (Framework Agreement)
START DATE : Nov-18
COMPLETION DATE : Nov-23
DESCRIPTION
A multi-year framework agreement for the performance of Project Management Contract "PMC" services for EPC Contracts. This scope include the treatment of oil production, gas processing plant and produced water treatment.

Safety Study of Anokyi Mainline Compressor Station (AMCS) EPCC Project
SCOPE OF WORK :
LOCATION : Ghana
DURATION : 6 months
START DATE : Nov-18
COMPLETION DATE : May-19
DESCRIPTION
To conduct the following study for the Anokyi Mainline Compressor Station (AMCS) EPCC Project of Meridian Logistic and Engineering (MLE) on behalf of Ghana National Gas Company
SIMOPS study;
HAZOP study;
LOPA study;
SIL study; and
QRA study.

On-Site Translation and Interpretation Support for the West Qurna (Phase 2) Project
CLIENT :
SCOPE OF WORK :
LOCATION : Iraq
DURATION : 48 months
START DATE : Nov-18
COMPLETION DATE : Nov-22
DESCRIPTION
To provide manpower for On-Site Translation and Interpretation Support in connection with exploration, appraisal, development, and production of the West Qurna (Phase 2) Contract Area.

Provision of Project Support Services for West Qurna 2
SCOPE OF WORK :
LOCATION : Iraq
DURATION : 36 months
START DATE : Sep-18
COMPLETION DATE : Sep-21 Cancelled
DESCRIPTION
To provide manpower services for the Provision of Project Support Services for West Qurna 2 in the Republic of Iraq.

Rovuma LNG Project – Pioneer Camp & Optional Scopes
CLIENT :
SCOPE OF WORK :
LOCATION : Mozambique
DURATION : 3 months
START DATE : Jul-18
COMPLETION DATE : Oct-18
DESCRIPTION
Pre-Bid Engineering and Preparation of full Technical Proposal for the Provision of EPCC and O&M for Mozambique Rovuma Venture S.p.A (MRV) Pioneer Camp (150,000 m2) which includes offices, 500 bed accommodation, helipad and complete support facilities enable camp to be self-sufficient during operation. MRV may choose to expand the Pioneer Camp to 900–person (additional 400) and provide additional road infrastructure.

Peshkabir Gas Project
CLIENT :
SCOPE OF WORK :
LOCATION : Kurdistan Region of Iraq
DURATION : 8 Weeks
START DATE : Jun-18
COMPLETION DATE : Jul-18
DESCRIPTION
Engineering Support for the Peshkabir Gas Project to provide Pre-FEED team that shall perform engineering to enable a FEED contract to be awarded for the Peshkabir Gas Project Facilities at the Peshkabir, Tawke and Fishkhabour sites and provide all records / documentation necessary for the complete performance of this scope.

Provision of Engineering, Procurement, Construction and Commissioning (EPCC) of Garraf Central Control Building (GCCB)
SCOPE OF WORK :
LOCATION : Iraq
DURATION : 18 months
START DATE : Sep-17
COMPLETION DATE : Mar-19
DESCRIPTION
Detailed engineering, architecture, and commissioning support for the complete GCCB, including Architecture, civil/structure, Honeywell control systems, Telecommunication, phone/LAN systems, and complete Electro/mechanical design.

Provision to Perform Plant Safe Operating Limits Gap Analysis and Produce the Latest Revision of Safe Operating Limit Documents
SCOPE OF WORK :
LOCATION : Iraq
DURATION : 5 months
START DATE : Jul-17
COMPLETION DATE : Dec-17
DESCRIPTION
Perform the First Commercial Production (FCP) and Offsite Facility Safe Operating Limit (SOL) latest revision through the following process:
Perform SOL Needs Assessment and Identify SOL Gap Analysis;
Establish SOL Mapping Exercise;
Prioritization of SOL documents and Gap Closure;
Creating and Updating of SOL Documents to the latest revision.

Provision of Engineering, Fabrication, Installation, Execution and Commissioning of Well Tie-Ins and Other Construction Services for Petronas Carigali Iraq Holding B.V. Garraf Operations
SCOPE OF WORK :
LOCATION : Iraq
DURATION : 24 months [with one (1) year extension
START DATE : Mar-17
COMPLETION DATE : Mar-19 [extend until Sept-20]
DESCRIPTION
Detailed engineering and commissioning support for different well pads Tie-in.

Provision to Perform Process Safety Information (PSI) Needs Analysis
SCOPE OF WORK :
LOCATION : Iraq
DURATION : 4 months
START DATE : Jan-17
COMPLETION DATE : May-17
DESCRIPTION
To deliver the complete Process Safety Information (PSI) Needs Analysis Report including but not limited to:
Process Safety Information (PSI) Needs Analysis Report;
Presentation material outlining the salient point of the report;
Native simulation files.

SIL Verification of Field Instruments – Paraffinic Naphtha Tanks Replacement (ADGAS) Project
SCOPE OF WORK :
LOCATION : UAE
DURATION : 3 months
START DATE : Jun-16
COMPLETION DATE : Sep-16
DESCRIPTION
Assist ADGAS and Target Engineering Const. Co. (LLC) by performing SIL Verification for the Paraffinic Naphtha Tanks Replacement Project.

Supply and Delivery (Separate RFQs)
CLIENT :
SCOPE OF WORK :
LOCATION : Kurdistan Region of Iraq
DURATION : -
START DATE : Sep-16
COMPLETION DATE : Oct-20
DESCRIPTION
Supply and Delivery of the following:
Multifunctional Electrical Meter
Mass Flow Meter
Universal Charging and Testing Unit FPU-1 (FPU-1-250-F-2.5-G3-A3-K)
Thermal Imager (FLK-TIS75 9HZ, Thermal Imager, Manual Focus)
Endress & Hauser Liquiphant FTL51
Honeywell Analytics Handheld Interrogator ATEX Certified (4V0 software) for Optima, Optima Plus and Excel.

Provision of Project Management Consultancy (PMC) for Sustained Production and Related Facilities
CLIENT :
SCOPE OF WORK :
LOCATION : Iraq
DURATION : 24 months
START DATE : Aug-16
COMPLETION DATE : Aug-18
DESCRIPTION
Reservoir, Source Water Plant 1 (SWP1) Expansion and Water Supply Pipeline (WSP).
To sustain the production of CPF1 and CPF2 in 2016, tie-in of new wells and existing well including the related facilities located in well pads by gathering crude oil and gas from the oil wells, transport through flow lines and/or trunk lines to CPF1/CPF2 is required.
Oil and Gas Gathering System, Pilot Test of Gas Lifting, Gas Lifting System, Water Injection System, Water Supply, Drain and Fire Fighting System, Power Supply System, Improvement to the Gas Turbine Power Plant, Instrumentation and Control System, Telecommunication System, Civil Works, Roads etc.

HAZOP Support for Avantgardre Project
CLIENT :
SCOPE OF WORK :
LOCATION : Nigeria
DURATION : 1 month
START DATE : Mar-16
COMPLETION DATE : Apr-16
DESCRIPTION
Expert technical support for HAZOP review of FPSO Project skid packages.

FPSO Project
CLIENT :
SCOPE OF WORK :
LOCATION : Nigeria
DURATION : 1 month
START DATE : Feb-16
COMPLETION DATE : Mar-16
DESCRIPTION
Calculation and design review of pumps in FPSO Skid.

Provision of Manpower Support
CLIENT :
SCOPE OF WORK :
LOCATION : Kurdistan Region of Iraq
DURATION : 6 months
START DATE : Feb-16
COMPLETION DATE : Aug-16
DESCRIPTION
Manpower Support to Hunt Oil Project in Kurdistan.

Different Projects
CLIENT :
SCOPE OF WORK :
LOCATION : Algeria
DURATION : 24 months
START DATE : Dec-15
COMPLETION DATE : Dec-17
DESCRIPTION
Appointed by CPECC BEB to provide engineering support for their office in Dubai and provide engineers in different disciplines to support:
Algeria Projects Support.

Block 5A Evacuation Pipeline from Thar Jath to Palouge
SCOPE OF WORK :
LOCATION : South Sudan
DURATION : 1 month
START DATE : Aug-15
COMPLETION DATE : Sep-15
DESCRIPTION
HAZOP Study

Different Projects
CLIENT :
SCOPE OF WORK :
LOCATION : Nigeria
DURATION : 1 month
START DATE : Jun-15
COMPLETION DATE : Jul-15
DESCRIPTION
Process and Piping review of Water bath heaters and Slug catcher design. Scope involved review of P&ID’s, Datasheets, and other design documentation to ensure the adequacy of the design and correctness of Material Take offs
Engineering works for Slug Cather and Fuel gas skid. Preparation of Nozzle Orientation, Piping Isometrics, Piping Supports design, cable routing for Electrical and instrumentation inside the skids.
Process review of Water bath heaters. P&ID’s, Datasheets and document review and verification of Water bath heaters and Material Take off review of the skids.

ADCO RMS stations upgrade Project
CLIENT :
SCOPE OF WORK :
LOCATION : UAE
DURATION : 1 month
START DATE : Apr-15
COMPLETION DATE : May-15
DESCRIPTION
Provided support for Mechanical handling study, RAM study, Datasheets and Specifications of Mechanical Equipment.

Gas Treatment Plant at Khurmala Dome Field (EPC Phase)
SCOPE OF WORK :
LOCATION : Iraq
DURATION : 1 month
START DATE : Apr-15
COMPLETION DATE : May-15
DESCRIPTION
HAZOP Review

Provision of Project Management Consultancy (PMC) Services for CPF3 and Associated Facilities
CLIENT :
SCOPE OF WORK :
LOCATION : Iraq
DURATION : 36 months
START DATE : Apr-15
COMPLETION DATE : Apr-18
DESCRIPTION
Halfaya Oil Field CPF3 Expansion 200k BOPD to 400k BOPD.
Carry out the PMC for PetroChina Halfaya CPF3 Iraq:
Oil and Gas Train Units;
Gas Compression Systems;
Gathering Facilities (GRS); and
Roads, Camps, others.
Improvement to the Gas Turbine Power Plant
Completion and Commissioning of Gas Lift Compression Plant.
Provision of all site procedures, HSE, QA/QC, etc. and PMC Team for Project, Engineering & Construction Management of the Project Execution Phase.

Afungi Pioneer Camp EPC
CLIENT :
SCOPE OF WORK :
LOCATION : Mozambique
DURATION : 3 months
START DATE : Mar-15
COMPLETION DATE : Jun-15
DESCRIPTION
Proposal and pre-bid engineering

Takreer Refinery Shutdown jobs
CLIENT :
SCOPE OF WORK :
LOCATION : UAE
DURATION : 1 month
START DATE : Feb-15
COMPLETION DATE : Mar-15
DESCRIPTION
Proposal support

Design-Review ADCO 51 OGD Wells and IA Compressor Upgrade
CLIENT :
SCOPE OF WORK :
LOCATION : UAE
DURATION : 1 month
START DATE : Feb-15
COMPLETION DATE : Mar-15
DESCRIPTION
Design review support

Supporting OiLSERV on Various Projects
CLIENT :
SCOPE OF WORK :
LOCATION : Kurdistan Region of Iraq
DURATION : -
START DATE : Dec-14
COMPLETION DATE : Dec-22
DESCRIPTION
Engineering Support for different Projects for DNO, HUNT OIL, TAQA, GAS PLUS, CHEVRON and EXXON. The scope includes design, pre-commissioning of different capacity of EPF facilities.

Project Management Services Agreement
CLIENT :
SCOPE OF WORK :
LOCATION : Iraq
DURATION : 18 months
START DATE : May-14
COMPLETION DATE : Nov-15
DESCRIPTION
High Priority Surveys for Common Seawater Supply Project (SOC)
Provided Project Management Services and related deliverables for High Priority Surveys which includes managing the subcontractors for Unexploded Ordnance (UXO) Survey, Topographical Survey, Geotechnical / Geophysical Survey, Bathymetric Survey, MetOcean Survey and Water Quality Sampling.
To manage contractual matters between Petrolinvest and subcontractors.

FEED and Detailed Engineering
CLIENT :
SCOPE OF WORK :
LOCATION : Iraq
DURATION : 14 months
START DATE : Sep-13
COMPLETION DATE : Jan-15
DESCRIPTION
Appointed by CPE to establish their Dubai office in accordance with Best International Practices.
Worked with CPE Management to provide Corporate Procedures – HSE, QA/QC, Procurement, etc. to obtain ISO qualification for the Dubai Office.
Provided Senior Engineer Teams for execution of Major Projects in Iraq:
Different projects for Petronas-Iraq;
Halfaya Works for PetroChina-Iraq.

Confidential
CLIENT :
SCOPE OF WORK :
LOCATION : Confidential
DURATION : 2 months
START DATE : Jul-13
COMPLETION DATE : Sep-13
DESCRIPTION
Carry out the HAZOP, HAZID and SIL Study for Oil and Gas Facility.

Gas Processing Plant-Ghana
SCOPE OF WORK :
LOCATION : Ghana
DURATION : 21 months
START DATE : Mar-13
COMPLETION DATE : Dec-14
DESCRIPTION
PMC Service for Sinopec Ghana Gas Processing Plant:
2x150MMscfd Gas Processing Plant (GPP);
Offshore Pipeline;
40MW Gas Turbine Power Plant;
Roads, Camps, others.
ExidaSP has provided a team to the Detailed Engineering, Construction, Procurement and Commissioning phase 1 of the Project.

Confidential
CLIENT :
SCOPE OF WORK :
LOCATION : Confidential
DURATION : 2 months
START DATE : Feb-13
COMPLETION DATE : Apr-13
DESCRIPTION
Carry out the HAZOP, HAZID and SIL Study for Oil and Gas Facility.

Provision of Project Management Consultancy (PMC) for Halfaya Oil Field Surface Facility Phase II
CLIENT :
SCOPE OF WORK :
LOCATION : Iraq
DURATION : 31 months
START DATE : Sep-12
COMPLETION DATE : Apr-15
DESCRIPTION
Halfaya Oil Field Phase 2 Expansion
100k BOPD to 200k BOPD
Carry out the PMC for PetroChina Halfaya Phase 2-Iraq:
Oil and Gas Train Units;
Gas Compression Systems;
Lift Compression Systems
150MMscfd Gas Receiving Station (GRS);
3x10MW Gas Turbine Power Plant;
Roads, Camps, others.
Provision of all site procedures, HSE, QA/QC, etc. and PMC Team for Project, Engineering & Construction Management of the Project Execution Phase.

HAZOP and or HAZID and SIL Study
CLIENT :
SCOPE OF WORK :
LOCATION : Iraq
DURATION : 1 month
START DATE : Apr-12
COMPLETION DATE : May-12
DESCRIPTION
Carry out the HAZOP and HAZID Study for Halfaya Phase 1 Oil and Gas Facility.

DNO North Iraq Topping Facility
SCOPE OF WORK :
LOCATION : Kurdistan Region of Iraq
DURATION : 1 month
START DATE : Dec-08
COMPLETION DATE : Dec-08
DESCRIPTION
Safety Design Review - DNO North Iraq Topping Facility.


Completed Projects