CLIENT | Kurdistan Pipeline Company Pte Ltd |
PROJECT TITLE | FEED Design of Fire Suppression System |
PROJECT DESCRIPTION | FEED for Fire Suppression System at three main stations of KPS1, KPS2 and RETM. |
SCOPE OF WORK | Engineering |
PROJECT LOCATION | Kurdistan, Iraq |
DURATION | 32 Weeks |
START DATE | Feb-22 |
COMPLETION DATE | Sep-22 |
CLIENT | Kurdistan Pipeline Company Pte Ltd | |||||
PROJECT TITLE | Engineering Study for Rectification of Electrical Defects at KPS0 Station | |||||
PROJECT DESCRIPTION | Engineering study for rectifications works on defective electrical equipment, material, components and instruments. The works include investigation, engineering study, design and engineering documentation and drawings for the systems. | |||||
SCOPE OF WORK | Engineering | |||||
PROJECT LOCATION | Kurdistan, Iraq | |||||
DURATION | 16 Weeks | |||||
START DATE | Jan-22 | |||||
COMPLETION DATE | May-22 |
CLIENT | Gulf Keystone Petroleum International Ltd. | ||||||||||
PROJECT TITLE | Provision Of Engineering Call-Off Services for Phases 1B, 1C and 1D | ||||||||||
PROJECT DESCRIPTION | Provision of Engineering support on an ad-hoc Call Off basis in developing
the Shaikan Field in Northern Kurdistan. |
||||||||||
SCOPE OF WORK | Engineering (GSA) | ||||||||||
PROJECT LOCATION | Kurdistan, Iraq | ||||||||||
DURATION | 24 Months + 12 Months Extension (Optional) | ||||||||||
START DATE | Jan-22 | ||||||||||
COMPLETION DATE | Jan-25 |
CLIENT | TAQA Atrush BV |
PROJECT TITLE | Provision of Engineering and Site support Service |
PROJECT DESCRIPTION | Providing PMC Services (E&I and Mechanical Site Works) to support TAQA’s operation in Atrush Block. |
SCOPE OF WORK | PMC |
PROJECT LOCATION | Kurdistan, Iraq |
DURATION | 12 Months |
START DATE | Aug-21 |
COMPLETION DATE | Aug-22 |
CLIENT | Meridien Logistic and Engineering (MLE) For behalf of Ghana National Gas Company | |||||
PROJECT TITLE | Safety Study of Anokyi Mainline Compressor Station (AMCS) Phase II EPCC Project | |||||
PROJECT DESCRIPTION | To conduct the following study for the Anokyi Mainline Compressor Station (AMCS) Phase II EPCC Project of Meridian Logistic and Engineering (MLE) on behalf of Ghana National Gas Company: • SIMOPS study; • HAZOP study; • SIL (LOPA) study; • FERA; and • QRA study. |
|||||
SCOPE OF WORK | Study | |||||
PROJECT LOCATION | Ghana | |||||
DURATION | 6 Months | |||||
START DATE | May-21 | |||||
COMPLETION DATE | Oct-21 |
CLIENT | RN-Harir -Bejil Pte. Ltd | ||||||||||
PROJECT TITLE | Provision of Engineering and Design Services for the Block 11 Field Development Projects | ||||||||||
PROJECT DESCRIPTION | Concept, FEED and Detailed Engineering for Block 11 Field: • SO#1 – Modernization of Bejil EWT Facilities (Stage 1) and Well BJ-11 Hook-up to the Existing Infrastructure Project Stage: FEED Status: Completed • SO#2 – Engineering and Design for Re-Construction of Existing and Construction of New Roads for the Well Pads Mirawa 1 and Mirawa 2 • SO#3 – IT and Telecom Infrastructure • SO#4 – Engineering and Design for Construction of Roads for the Wellpad Mirawa 1 • SO#5 – Bejil 2A Wellhead Facilities and Associated Gathering System Pipeline to EWT |
||||||||||
SCOPE OF WORK | Engineering (GSA) | ||||||||||
PROJECT LOCATION | Kurdistan, Iraq | ||||||||||
DURATION | 24 Months [plus one (1) year optional extension] | ||||||||||
START DATE | Mar-21 | ||||||||||
COMPLETION DATE | Feb-23 [plus one (1) year optional extension] |
CLIENT | Gazprom Neft Middle East B.V. | |
PROJECT TITLE | Design and Engineering Services | |
PROJECT DESCRIPTION | Provision of Design and Engineering Services for Firefighting System at CPF Sarqala-1 Wellsite, Garmian Block, Kurdistan. | |
SCOPE OF WORK | FEED & Detailed Engineering | |
PROJECT LOCATION | Kurdistan, Iraq | |
DURATION | Approx. 18 Months | |
START DATE | Oct-20 | |
COMPLETION DATE | Feb-22 |
CLIENT | Italfluid Geoenergy SRL | |
PROJECT TITLE | Provision of Leased Oil Train (LOT), Garraf, Iraq Provision of O&M Services (Garraf Project) | |
PROJECT DESCRIPTION | To provide Operation & Maintenance (O&M) Services for Petronas Carigali Iraq Holding B.V. on behalf of Italfluid. This include pre-commissioning and commissioning for different types of instruments and also calibration of the custody metering skid for the LOT. | |
SCOPE OF WORK | O&M | |
PROJECT LOCATION | Iraq | |
DURATION | 12 Months | |
START DATE | Feb-20 Under HOLD | |
COMPLETION DATE | Jan-22 Under HOLD |
CLIENT | Italfluid Geoenergy SRL | |
PROJECT TITLE | Provision of Leased Oil Train (LOT), Garraf, Iraq Consultancy Agreement for Site Works | |
PROJECT DESCRIPTION | Provision of Site/Construction Supervision for Petronas Carigali Iraq Holding B.V. on behalf of Italfluid. This include testing and calibration of the control systems. | |
SCOPE OF WORK | Site Supervision | |
PROJECT LOCATION | Iraq | |
DURATION | 18 Months | |
START DATE | Aug-19 | |
COMPLETION DATE | Feb-21 Under HOLD |
CLIENT | Italfluid Geoenergy SRL | ||
PROJECT TITLE | Provision of Leased Oil Train (LOT), Garraf, Iraq Design, Supply and Configuration of DCS & Integrated Safety System | ||
PROJECT DESCRIPTION | Provision of Design, Supply and Configuration of DCS & Integrated Safety System for Leased Oil Train, Petronas, Iraq. This include testing and calibration of the control systems. |
||
SCOPE OF WORK | Engineering | ||
PROJECT LOCATION | Iraq | ||
DURATION | 8 Months | ||
START DATE | May-19 | ||
COMPLETION DATE | Jan-20 SAT is not completed yet due to the Pandemic |
CLIENT | TAQA Atrush BV |
PROJECT TITLE | Provision of Engineering Services |
PROJECT DESCRIPTION | To perform Feasibility studies and front-end engineering studies, Detailed design activities including preparation of procurement documentation (invitation to tender packages) and technical bid evaluations, provision of personnel to work within TAQA’s organization, and provision of any other work and Services incidental to the foregoing including ‘as building’ documentation, survey works, minor plant changes, etc.
• Call-Off Order No. 01 – Transition of TAQA documents from the previous templates to the new corporate branded templates. |
SCOPE OF WORK | Engineering (GSA) |
PROJECT LOCATION | Kurdistan, Iraq |
DURATION | 30 Months |
START DATE | Nov-19 |
COMPLETION DATE | May-22 |
CLIENT | BL Energy |
PROJECT TITLE | Provision of Engineering Services |
PROJECT DESCRIPTION | To provide Engineering Support for different ongoing Projects. |
SCOPE OF WORK | Engineering |
PROJECT LOCATION | Iraq / UAE |
DURATION | – |
START DATE | Oct-19 |
COMPLETION DATE | On Going |
CLIENT | LUKOIL Mid-East Limited |
PROJECT TITLE | On-Site Translation and Interpretation Support for the West Qurna (Phase 2) Project |
PROJECT DESCRIPTION | To provide manpower for On-Site Translation and Interpretation Support in connection with exploration, appraisal, development and production of the West Qurna (Phase 2) Contract Area. |
SCOPE OF WORK | Manpower Supply |
PROJECT LOCATION | Iraq |
DURATION | 48 months |
START DATE | Nov-18 |
COMPLETION DATE | Nov-22 |
CLIENT | SONATRACH | |
PROJECT TITLE | Framework Agreement for a Project Management Contract | |
PROJECT DESCRIPTION | A multi-year framework agreement for the performance of Project Management Contract “PMC” services for EPC Contracts. | |
SCOPE OF WORK | PMC | |
PROJECT LOCATION | Algeria | |
DURATION | 60 months (Framework Agreement) | |
START DATE | Nov-18 | |
COMPLETION DATE | Nov-23 |
CLIENT | OILSERV |
PROJECT TITLE | Different Projects |
PROJECT DESCRIPTION | Engineering Support for different ongoing Projects and Proposals for DNO, HUNT OIL, TAQA, GAS PLUS, CHEVRON, PETRONAS, LUKOIL and EXXON. This Scope includes installation supervisions, mechanical and piping testing, E/I testing and calbirations. |
SCOPE OF WORK | Detailed Design |
PROJECT LOCATION | Kurdistan, Iraq |
DURATION | Not Defined |
START DATE | Dec-14 |
COMPLETION DATE | Ongoing |