Clear
Different Projects 2

ETAP

Ongoing
Client
HKN Atrush Ltd.
Scope of Work

Study

Location
Kurdistan Region of Iraq
Duration
4 Months
Start Date
2025-06-01
Completion Date
2025-10-01
Description

Update ETAP model and conduct Power System Studies to verify system adequacy, identify limitations, and recommend improvements for safe and reliable operation under current and future scenarios

Block 5A Evacuation Pipeline from Thar Jath to Palouge

Atrush Gas Utilization – Feasibility & Design of Amine Unit & Hot Oil System

Ongoing
Client
HKN Atrush Ltd.
Scope of Work

Feasibility& Design

Location
Kurdistan Region of Iraq
Duration
8.00 Weeks
Start Date
2026-07-01
Completion Date
2026-09-01
Description

Provide all required engineering expertise, tools, software, and resources to complete the feasibility study and engineering design for the inclusion of a new amine unit, thermal oxidizer, hot oil pumps, and associated generator/dual fuel power study

Technical Service for FEED for Full Field Production Facilities of Eridu Oil Field Development Block 10 Project

General Engineering Services On Call Off Basis

Ongoing
Client
Geo-Jade
Scope of Work

GSA

Location
Iraq
Duration
24 Months
Start Date
2025-03-01
Completion Date
2027-03-01
Description

This scope of work covers surface facilities design, from PDP to conceptual design and FEED. Responsibilities include conducting a feasibility study, proposing a product evacuation plan, and delivering design services such as basic design, topographical and geotechnical surveys, technical proposals, cost estimation, technical scheme comparison, and PDP reports for the surface facility. Also provide engineering deliverables (drawings, specifications, datasheets) for COMPANY review and approval. Additionally, procurement support will also be included for developing material requisitions (MR), material take-offs (MTO), addressing technical queries (TQ), supporting technical bid evaluations, reviewing vendor drawings, participating in vendor technical meetings, and attending Factory Acceptance Testing (FAT) as required. These services aims to ensure seamless project execution and alignment with COMPANY standards. This scope include the treatment of oil production, gas processing plant and produced water treatment.

Pre-Bid Engineering Support for EPC of Mishrif Wellpad & Dammam Well Upgrades for West Qurna 2

Syria Tabbyah EPF – Detail Design

Ongoing
Client
Expro
Scope of Work

Detailed Engineering

Location
Syria
Duration
8 weeks
Start Date
2026-09-01
Completion Date
2026-11-01
Description

Detail engineering design services for Electrical, Instrumentation & Control, Piping, and Civil Structural for an EPF. Fast-track project for full delivery of EPF within 16-weeks.

Provision of Electrical, Instrument & Mechanical Manpower Service

PESHKABIR. 11/33 kV Transformers Protection & Wiring Rectification

Ongoing
Client
DNO Technical Services
Scope of Work

ETAP Study

Location
Kurdistan Region of Iraq
Duration
1.00 Months
Start Date
2026-07-01
Completion Date
2026-08-01
Description

Electrical engineering study for the 11/33 kV distribution system (Phase 1) at DNO's Baeshiqa facilities. Scope covers validation of existing short circuit calculation (SCC) and overcurrent protection settings (OPS) reports against international standards, assessment of the neutral earthing system to determine the requirement and feasibility of overcurrent ground fault protection, and production of a protection settings report where applicable. Deliverables: NER sizing calculation and relay protection study report.
Control & Connection diagram for Transformers and NERs
Updation of UPS DB SLD
Preparation of Cable Schedule
EF Relay setting report for 11kv Switchgear Incomers

Provision of Engineering Services (Baeshiqa)

Provision of Engineering Services (Baeshiqa)

Ongoing
Client
DNO Iraq AS
Scope of Work

GSA

Location
Kurdistan Region of Iraq
Duration
24 Months
Start Date
2022-10-01
Completion Date
2024-10-01
Description

Perform conceptual engineering (Identify, assess, select, define) options, preparation of conceptual reports, project controls, procurement support, detailed design including all analyses, preparation of operation, maintenance, commissioning, and start-up assistance to Company's Operations Group as required and for the provision of all records I documentation necessary for the complete performance of the Work.
Responsible for all aspects of the Services, regarding Health, Safety, Security and Environmental (HSSE) performance, quality management, schedule, cost, and functionality.
The Services to be provided under the Contract may include, but not be limited to:
Feasibility studies and frontend engineering studies for the process facility;
Detailed design activities for the process facility, offsite, pipeline, and OHL, and that includes preparation of procurement documentation (invitation to tender packages) and technical bid evaluations. This scope include the treatment of oil production, gas processing plant and produced water treatment.

General Engineering Services for Projects in MEDC (2025-2027)

Provision of Engineering Services for LPG Plant Operations

Ongoing
Client
Crescent Petroleum / Pearl Petroleum Company Limited (PPCL)
Scope of Work

GSA

Location
Kurdistan Region of Iraq
Duration
24 Months
Start Date
2024-10-01
Completion Date
2026-10-01
Description

Engineering support focuses on front-end engineering, executed via Call-Off Orders under a Master Services Agreement. Scopes range from feasibility studies, providing technical and commercial evaluations, to FEED studies for larger projects, delivering multidisciplinary outputs like P&IDs, process flow diagrams, 3D models, schedules, and cost estimates. These services support informed project decisions on feasibility and viability.

Technical Service for FEED for Full Field Production Facilities of Eridu Oil Field Development Block 10 Project

Engineering Services for LPG Plant Operations

Ongoing
Client
Crescent Petroleum / Pearl Petroleum Company Limited (PPCL)
Scope of Work

GSA

Location
Kurdistan Region of Iraq
Duration
3 Months
Start Date
2025-05-01
Completion Date
2026-10-01
Description

Provision of specialized engineering service for Crescent Petroleum's Khor Mor site in the Kurdistan Region of Iraq. This scope include the treatment of oil production, gas processing plant and produced water treatment.

Engineering Study for Rectification of Electrical Defects at KPS0 Station

Call-Off Order for Hire of Consultant – Senior Electrical Engineer for KM OPS

Ongoing
Client
Crescent Petroleum / Pearl Petroleum Company Limited (PPCL)
Scope of Work

Manpower

Location
Kurdistan Region of Iraq
Duration
3 Months
Start Date
2026-03-01
Completion Date
2026-06-01
Description

Supply of Manpower (Senior Electrical Engineer)

Detailed Design for Business Continuity - Gas In, Gas Out

Technical Services for General Engineering Services of MEDC

Ongoing
Client
CHINA PETROLEUM ENGINEERING CO, LTD (DUBAI BRANCH)
Scope of Work

GSA

Location
Dubai, UAE
Duration
24 Months
Start Date
2025-12-01
Completion Date
2027-11-01
Description

Provide required Technical Service to support COMPANY for carrying out design engineering, detailed engineering, technical support for procurement activities such as; Material Requisitions (MRs), Technical Bids Evaluations (TBEs) & Vendor Data Requirements (VDRs), as well as support for the project management, planning, control, cost control, document control, construction, and commissioning Work, as required.

Technical Service for FEED for Full Field Production Facilities of Eridu Oil Field Development Block 10 Project

Technical Service for FEED for Full Field Production Facilities of Eridu Oil Field Development Block 10 Project

Ongoing
Client
CHINA PETROLEUM ENGINEERING CO, LTD (DUBAI BRANCH)
Scope of Work

FEED

Location
Iraq
Duration
6 Months
Start Date
2025-05-01
Completion Date
2025-11-01
Description

This scope of work covers surface facilities design, from PDP to conceptual design and FEED.This scope include the treatment of oil production, gas processing plant and produced water treatment.

Technical Service for Engineering Projects in MEDC for Year 2024 & 2025

Technical Service for Engineering Projects in MEDC for Year 2023 & 2025

Ongoing
Client
CHINA PETROLEUM ENGINEERING CO, LTD (DUBAI BRANCH)
Scope of Work

GSA

Location
Abu Dhabi and Dubai, UAE
Duration
24 Months
Start Date
2023-09-01
Completion Date
2025-09-01
Description

Provide required Technical Service to support COMPANY for carrying out design engineering, detailed engineering, technical support for procurement activities such as; Material Requisitions (MRs), Technical Bids Evaluations (TBEs) & Vendor Data Requirements (VDRs), as well as support for the project management, planning, control, cost control, document control, construction, and commissioning Work, as required.
Conducted Flow Assurance Studies as a part of the GSA.