SO1 – To perform FEED of Modernization of Beiji EWT Facilities (Stage 1) and Well BJ-11 Hookup to the Existing Infrastructure.

The project scope includes several process facility modifications to the existing plant, including the hookup of the new BJ-11 well to the existing infrastructure with associated wellhead control systems, future metering and chemical injection provisions, and fire and gas systems. Additional upgrades include replacement of the existing Gas Equalization System (GES) piping and blow cases, installation of interconnecting piping for flexible storage tank operation, and provision of new sampling devices to improve oil and water quality monitoring.

The scope also includes construction of stormwater and industrial wastewater drainage systems, installation of a stationary oil off-loading facility for road tankers, vacuum trucks, and barrels/IBCs, and provision of fresh water supply points for flushing and salt deposition prevention. Existing facility utilities, including nitrogen, instrument air, and power, will support the new equipment, while a UPS with two-hour battery backup will provide emergency power for the Wellhead Control Panel.

Provision of Engineering and Design Services for the Block 11 Field Development Projects

Concept, FEED and Detailed Engineering for Block 11 Field.
The Services to be provided under the Contract may include, but not be limited to:
Feasibility studies and frontend engineering studies for the process facility;
Detailed design activities for the process facility, offsite, pipeline, and OHL, and that includes preparation of procurement documentation (invitation to tender packages) and technical bid evaluations;
Conducted Flow Assurance Study for Bejil Field Soluforce Production Trunkline;
Conducted Flow Assurance Study for Soluforce Water Disposal System.
This scope includes the leased EPF early production facility of 10,000 BBL per day and the upgrade of existing treatment of oil production, gas processing plant and produced water treatment.

Provision of Engineering and Design Services for Block 8

Concept, FEED and Detailed Engineering for Block 8 Oil and Gas Field.
The Services to be provided under the Contract may include, but not be limited to:
Feasibility studies and frontend engineering studies for the process facility;
Detailed design activities for the process facility, offsite, pipeline, and OHL, and that includes preparation of procurement documentation (invitation to tender packages) and technical bid evaluations. This scope include the treatment of oil production, gas processing plant and produced water treatment.

Provision of Engineering, Procurement, Construction and Commissioning (EPCC) of Garraf Central Control Building (GCCB)

Detailed engineering, architecture, and commissioning support for the complete GCCB, including Architecture, civil/structure, Honeywell control systems, Telecommunication, phone/LAN systems, and complete Electro/mechanical design.

Provision of Engineering, Fabrication, Installation, Execution and Commissioning of Well Tie-Ins and Other Construction Services for Petronas Carigali Iraq Holding B.V. Garraf Operations

Detailed engineering and commissioning support for different well pads Tie-in.

Provision to Perform Process Safety Information (PSI) Needs Analysis

To deliver the complete Process Safety Information (PSI) Needs Analysis Report including but not limited to:
Process Safety Information (PSI) Needs Analysis Report;
Presentation material outlining the salient point of the report;
Native simulation files.

Provision to Perform Plant Safe Operating Limits Gap Analysis and Produce the Latest Revision of Safe Operating Limit Documents

Perform the First Commercial Production (FCP) and Offsite Facility Safe Operating Limit (SOL) latest revision through the following process:
Perform SOL Needs Assessment and Identify SOL Gap Analysis;
Establish SOL Mapping Exercise;
Prioritization of SOL documents and Gap Closure;
Creating and Updating of SOL Documents to the latest revision.

Project Management Services Agreement

High Priority Surveys for Common Seawater Supply Project (SOC)
Provided Project Management Services and related deliverables for High Priority Surveys which includes managing the subcontractors for Unexploded Ordnance (UXO) Survey, Topographical Survey, Geotechnical / Geophysical Survey, Bathymetric Survey, MetOcean Survey and Water Quality Sampling.
To manage contractual matters between Petrolinvest and subcontractors.

Provision of Project Management Consultancy (PMC) Services for CPF3 and Associated Facilities

Halfaya Oil Field CPF3 Expansion 200k BOPD to 400k BOPD.
Carry out the PMC for PetroChina Halfaya CPF3 Iraq:
Oil and Gas Train Units;
Gas Compression Systems;
Gathering Facilities (GRS); and
Roads, Camps, others.
Improvement to the Gas Turbine Power Plant
Completion and Commissioning of Gas Lift Compression Plant.
Provision of all site procedures, HSE, QA/QC, etc. and PMC Team for Project, Engineering & Construction Management of the Project Execution Phase.

Provision of Project Management Consultancy (PMC) for Sustained Production and Related Facilities

Reservoir, Source Water Plant 1 (SWP1) Expansion and Water Supply Pipeline (WSP).
To sustain the production of CPF1 and CPF2 in 2016, tie-in of new wells and existing well including the related facilities located in well pads by gathering crude oil and gas from the oil wells, transport through flow lines and/or trunk lines to CPF1/CPF2 is required.
Oil and Gas Gathering System, Pilot Test of Gas Lifting, Gas Lifting System, Water Injection System, Water Supply, Drain and Fire Fighting System, Power Supply System, Improvement to the Gas Turbine Power Plant, Instrumentation and Control System, Telecommunication System, Civil Works, Roads etc.